Another super busy and productive day today

We are continuing installing formwork around the plinths ready for screeding. 1. We are going to bring the redundant substation back into use. 2. We are removing the old 11kv swich gear and cabling. At the same time installing a … Continue reading

Posted in Uncategorized | Leave a comment

Another busy morning at Sandfields Pumping Station

Shuttering sorted for one plinth. It just needs fixing in place ready for the next stage concrete, levelling and then the final part tiling.  A level floor is now getting closer. Engineering team are back with cleaning the engine after … Continue reading

Posted in Uncategorized | 1 Comment

July Newsletter

https://mailchi.mp/9fa19340b2c2/lichfield-waterworks-trust-may-newletter-6200613

Posted in Uncategorized | Leave a comment

These engineers are expensive, but they are good……

The heavy work has been completed by the builders. They have chiselled away over four tonnes of sold mass reenforced concrete. It’s now time for some precision (building) work, enter the engineering team. Their task is to square things up, … Continue reading

Posted in Uncategorized | Tagged , , , , | 1 Comment